|
 |
 |
 |
 |
Microsoft Knowledge Base Article
This article contents is Microsoft Copyrighted material.
©2005-©2007 Microsoft Corporation. All rights reserved. Terms
of Use |
Trademarks
Article ID: 141733 - Last Review: September 19, 2011 - Revision: 5.0 PRJ: How to Build a Hammock TaskThis article was previously published under Q141733
A "hammock" task is dependent on external dates for both its start and finish dates and, ultimately, its duration. The name, hammock task, is
derived from the way a hammock's shape is determined by the distance
between the points to which it is attached.
As scheduled dates in other tasks change, the duration and start and/or
finish dates of the hammock task change as well. In other words, given
three tasks A, B, and C, task B must start on some date from task A (date
A) and task B must finish on some date from task C (date C). For an
illustration of this task B, see Example 1.
Example 1--Hammock Task B
The span of time between dates A and C dictate the available time to
accomplish task B. As Date A changes, the start date for task B changes as
well; If date C moves, task B must finish appropriately. The difference
between dates A and C is the duration for task B. See example 2.
Example 2--Date A Late, Date C EarlyTo build a hammock task between two other tasks in Microsoft Project 2007 and earlier versions, follow these steps: - Create or determine three tasks that correspond to A, B, and C in the
example above.
- Highlight the cell that contains date A (the date that will determine
when task B starts).
- On the Edit menu, click Copy (Cell).
- Highlight the cell that contains the Start date for task B (the hammock
task).
- On the Edit menu, click Paste Special, and click Paste Link.
- Highlight the cell that contains Date C (the date that will determine
when task B finishes).
- On the Edit menu, click Copy (Cell).
- Click the cell that contains the Finish date for task B (the hammock
task).
- Click Edit, click Paste Special, and click Paste Link.
To build a hammock task between two other tasks in Microsoft Project 2010, follow these steps: - Create or determine three tasks that correspond to A, B, and C in the example above.
- Highlight the cell that containes date A (the date that will determine when task B starts).
- On the Task tab, click copy.
- Highlight the cell that contains the Start date for task B (the hammock task).
- On the Task tab, select the Paste drop-down, and then click Paste Special. Select Paste Link and then click OK.
- Highlight the cell that contains Date C (the date that will dtermine when task B finishes).
- On the Task tab, click Copy.
- Click the cell that contains the finish date for task B (the hammock task).
- On the Task tab, select the Paste drop-down, and then click Paste Special. Select Paste Link and then click OK.
NOTE: The Date format on the Options dialog box muc be set to show time as well as date, such as Wed. 1/28/09 12:33 PM, otherwise the linked task will use the beginning of the day specified instead of the beginning of the next day. Notes and Cautions- Do not specify a predecessor for a hammock task. Only Paste Linked dates
will determine start and finish. You may specify predecessors for the
tasks from which dates are paste linked into the hammock task.
- A negative duration (finish date is before start) is not allowed.
Depending on the source of the dates, the hammock task may turn into a
milestone (zero duration) or erroneously calculate duration before the
finish date or after the start date.
- An OLE update is different from a calculation. You may not see expected
changes in the hammock task after calculating project. From the Edit
menu, click Links to edit/update OLE links (Paste Links). Alternatively,
press the F9 function key twice.
- Because the hammock task relies on other tasks for start/finish
information, anything that affects those other tasks (resource leveling,
constraints) will ultimately affect the hammock tasks dates.
- If the hammock task is a child to a summary task, it may inherit
predecessor behavior from the summary task that may affect its duration
and/or start and finish dates or create a circular relationship.
APPLIES TO- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 3.0 Standard Edition
- Microsoft Project 4.0 for Macintosh
- Microsoft Office Project Professional 2007
- Microsoft Office Project Professional 2003
- Microsoft Office Project Standard 2007
- Microsoft Office Project Standard 2003
- Microsoft Project 2002 Standard Edition
- Microsoft Project 2002 Professional Edition
- Microsoft Project Professional 2010
- Microsoft Project Server 2010
- Microsoft Project Standard 2010
Community Feedback System
Very often, it takes hours to solve a problem. Very often, you've looked high
and low, and have tried a lot of solutions. When you finally found it, chances
are, it was because someone else helped you. Here's your chance to give back.
Use our community feedback tool to let others know what worked for you and what
didn't.
Please also understand that the community feedback system is not warranted to be
correct, it's simply a system that we've built to let people try and help each
other. If something in a feedback response doesn't make sense to you, or you're
not comfortable making changes that the feedback talks about (like registry
edits), please consult a professional.
Thank you for using kbAlertz.com Feedback System.
-- Scott Cate
|
 |
 |
 |
 |
 |
 |
 |
| |